Fabrication-Bay Cranes Tutorial: Erection Step by StepNow
When loads get too big for forklifts and too precise for rough handling, teams turn to overhead cranes. This practical guide follows the journey from bare runways to a commissioned crane ready for service. You’ll see hoist and trolley setup—with the same checklists pro installers use.
Overhead Crane, Defined
At heart, a bridge crane is a bridge beam that spans between two runway beams, carrying a trolley-mounted hoist for precise, vertical picks. The result is smooth X-Y-Z motion: and lift via the hoist.
You’ll find them in fabrication bays, steel plants, power stations, oil & gas shops, precast yards, and logistics hubs.
Why they matter:
Controlled moves for large, expensive equipment.
Huge efficiency gains.
Lower risk during rigging, lifting, and transport inside facilities.
Support for pipelines, structural steel, and big machinery installs.
System Components We’re Installing
Runways & rails: runway girders with crane rail and clips.
End trucks: wheel assemblies that ride the rail.
Bridge girder(s): cambered and pre-wired.
Trolley & hoist: cross-travel carriage with lifting unit.
Electrics & controls: VFDs, radio remote, pendant.
Stops, bumpers & safety: end stops, buffers, travel limits.
Depending on capacity and span, the crane might be a single-girder 10-ton unit or a massive double-girder 100-ton system. The choreography is similar, but the scale, lift plans, and checks grow with the tonnage.
Pre-Install Prep
Good installs start on paper. Key steps:
Drawings & submittals: Freeze the GA and verify reactions with the structural team.
Permits/JSAs: Permit-to-work, hot work, working at height, rigging plans.
Runway verification: Check baseplates, grout pads, and anchor torque.
Power readiness: Lockout/tagout plan for energization.
Staging & laydown: Mark crane components with ID tags.
People & roles: Brief everyone on radio calls and stop-work authority.
Tiny survey errors balloon into hours of rework. Spend time here.
Alignment That Saves Your Wheels
If rails are off, nothing else will run true. Targets and checks:
Straightness & elevation: Laser or total station to set rail height.
Gauge (span) & squareness: Check centerlines at intervals; confirm end squareness and expansion joints.
End stops & buffers: Install and torque per spec.
Conductor system: Keep dropper spacing uniform; ensure collector shoe reach.
Log final numbers on the ITP sheet. Correct now or pay later in wheel wear and motor overloads.
Lifting the Bridge
Rigging plan: Softeners protect painted flanges. Dedicated signaler on radio.
Sequence:
Lift end trucks to runway level and set temporarily on blocks.
For double-girder cranes, lift both girders with a matched raise.
Use drift pins to align flange holes; torque to spec.
Verify camber and bridge square.
Prior to trolley install, bump-test long-travel motors with temporary power (under permit): confirm limit switch wiring. Lock out after test.
Hoist & Trolley
Trolley installation: Mount wheels, align wheel flanges, set side-clearances.
Hoist reeving: Check rope path, sheave guards, and equalizer sheaves.
Limits & load devices: Set upper/lower limit switches.
Cross-travel adjustment: Align trolley rails on a double-girder.
Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.
A smooth trolley with a quiet hoist is a sign of good alignment. Don’t mask issues with higher VFD ramps.
Power with Discipline
Power supply: Drop leads tagged and strain-relieved.
Drive setup: Enable S-curve profiles for precise positioning.
Interlocks & safety: Zone limits near doors or mezzanines.
Cable management: Secure junction boxes; label everything for maintenance.
Future you will too. If it isn’t documented, it didn’t happen—put it in the databook.
Trust but Verify
Inspection Test Plan (ITP): Hold/witness points for rail alignment, torque, electrical polarity, limit settings.
Torque logs: Re-check after 24 hours if required.
Level & gauge reports: Note any corrective shims.
Motor rotation & phasing: Document bump tests.
Functional tests: Jog commands, inching speeds, limits, overloads, pendant/remote range.
A tidy databook speeds client acceptance.
Ready for Work
Static load test: Hold at mid-span and near end stops; monitor deflection and brake performance.
Dynamic load test: Check sway, braking distances, and VFD fault logs.
Operational checks: Emergency stop shuts down all motions.
Training & handover: Operator basics, daily pre-use checks, rigging do’s & don’ts.
When the logbook is clean, the crane is officially in service.
Applications & Use Cases
Construction & steel erection: placing beams, trusses, and precast.
Oil & gas & power: generator and turbine assembly.
Steel mills & foundries: large part transfer.
Warehousing & logistics: bulk material moves with minimal floor traffic.
Once teams learn the motions, cycle times drop and safety improves.
Do It Safe or Don’t Do It
Rigging discipline: dedicated signaler and stop-work authority.
Lockout/Tagout: clear isolation points for electrical work.
Fall protection & edges: approved anchor points, guardrails on platforms, toe boards.
Runway integrity: no cracked welds, correct bolt grades, proper grout.
Duty class selection: match crane class to cycles and loads.
A perfect lift is the one nobody notices because nothing went wrong.
Keep It Rolling
Crab angle/drift: re-check runway gauge and wheel alignment.
Hot gearboxes: adjust brake air gap and reduce VFD decel.
Rope drum spooling: dress industrial shed rope and reset lower limit.
Pendant lag or dropout: antenna placement for radio; inspect festoon collectors.
Wheel wear & rail pitting: lubrication and alignment issues.
Little noises are messages—listen early.
Fast Facts
Overhead vs. gantry? Choose per site constraints.
Single vs. double girder? Span and duty class usually decide.
How long does install take? Scope, bay readiness, and tonnage rule the schedule.
What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.
What You’ll Take Away
If you’re a civil or mechanical engineer, construction manager, shop supervisor, or just a mega-project fan, this deep dive makes the whole process tangible. You’ll gain a checklist mindset that keeps cranes safe and productive.
Need a field bundle with JSA templates, rigging calculators, and commissioning sheets?
Get the toolkit now and cut hours from setup while boosting safety and QA/QC. Bookmark this guide and share it with your crew.
...